When i try to add a new job list - the card has an error - The precent complete value must be less than, or equal to 100. No matter what amount i put in - a error comes up.
Hi @GGC203
Thanks for your post. Does this happen to all new jobs? Are you trying to add a Header or a Detail Job? Could you go to the Job list window, go into each sub job of header job 'projects' > Take note of the Percent Complete figures > Zero out the percent figures > Once all amounts in the percent Complete field have been removed from every sub-job, see if the program allows for you to type in a figure into the new job >If it does accept it this time around, you can then go ahead and try inputting the relevant figures back into each sub-job window.
Let me know how you get on with this.
This was only for a detail job. I zeroed all percentages and seems to have solved problem.
Thank you