Good morningI ams till not understanding the time sheets to PayrollI enter the total hours and OT in the times sheets and add the various jobs requried (see pic one on the attachment)Then when I go to payroll to process it is not correct (see pic two). I have changed the standard hours (pic three) and I am still baffled as to why.The reason we need to do it this way is so we can job cost, the staff do go to different places through out the day and we need to job code the hours.Please advise if I am doing something incorrectThank you Anna
I appears to not have picked up the first days hours
Total hours on pay 40.5 Total hours on timesheet 48.75 difference 8.25 ( wed)
I cant see the period you have selected but make sure it is picking up 23/2 -1/3 in the pay period
Hope that helps
Lisa
AGREE
hours captured first and last dates are often missing,
bad programming - this creates costly rework!!!!!
Thanks Lisa, It wa the date that I was getting wrong. So much better
Cheers Anna